Transfers between Safran and Safran or P6 and P6

Modified on Thu, 16 Oct at 2:31 PM

TABLE OF CONTENTS


Introduction

When transferring data between Safran and Safran, or P6 and P6, IDE detects that each of the endpoints use the same Host System and therefore automatically adds some Host Specific settings at Activity and ResourceAssignment levels. The tables below show which fields are added for each of Safran and P6.

 

The list of fields for Safran

The list of fields that are automatically added to a transfer when source and destination is Safran.

 

DataTypeDescriptionHostSystemIlapTermNameILAPIdPlObjType
BooleanActivity duration fit flagSP_Act_activity_duration_fit_flagada9e6f0-247c-4fd5-a8a3-50525978dcbbActivity
BooleanActivity existence flagSP_Act_activity_existence_flaga5c41c5c-eef3-4dd0-b921-a11855d1795aActivity
IntegerFuture useSP_Act_analyse_opt36dc2378-3ed5-4ba6-9c5c-feae2a13331eActivity
FloatApproved variations quantitySP_Act_approved_vo_qty98eee131-f5ff-4477-93c4-e9256160ea75Activity
StringUnits for duration fieldSP_Act_duration_units5dacaeb9-8b05-4551-8e49-ffeb926311f4Activity
BooleanHammock flagSP_Act_hammock_flagaa967877-e2e1-4b7d-888e-77e53b46ba36Activity
IntegerFlag for “all job packs defined”SP_Act_job_flag66410e4d-d6e9-422e-9304-3e85376f824aActivity
IntegerIs activity manually progress updated? 1=yes 0=noSP_Act_manual_prog_flag4cf32a41-99de-4ea5-8439-1613382b2db4Activity
IntegerMinimum duration used with activity fit optionSP_Act_minimum_duration84fcad0d-1014-4a75-b40c-0bb1ccb1917bActivity
BooleanProgress out of sync flag Is set to 1 for activity during baseline update if volume progress and time progress is not matching for at least one resourceSP_Act_out_of_syncf93e9e22-f318-40eb-b916-da9ed08d5d95Activity
FloatTime percent completed – related to current_progressSP_Act_current_pc6a7a2b0b-e35e-4474-9da0-30bd47a6d9efActivity
IntegerRemaining duration analyzedSP_Act_remain_duration_analyzed3355a122-2fa3-43f9-b864-b7b1d1eafb8dActivity
StringRemarksSP_Act_remarksec64ad69-b27c-4c52-91af-04ec3ba180c0Activity
IntegerSub-Network IdSP_Act_subnetwork_ide14fda8d-5d16-48ee-ac06-88f642bff3c6Activity
StringFormating unit for the duration field (w=weeks d=days h=hours m=minutes)SP_Act_duration_formated62de6b-a2b8-42b4-b540-acaf383c81d3Activity





StringFormating unit for the duration field (w=weeks d=days h=hours m=minutes)SP_ResA_duration_format75027795-7146-461f-a614-7d60c1fedbe5ResourceUsage
IntegerFlag for inclusion in Rsh. Internal flag: current scope (configurable summary)SP_ResA_rsh_flag919ebb02-21ec-485c-975a-6d94f8ad80f6ResourceUsage
IntegerFlag for inclusion in Tsh Internal flag: total scope (configurable summary)SP_ResA_tsh_flag2f3dcd40-efee-4c0a-ad3d-1d36bfaa8302ResourceUsage
IntegerResource typeSP_ResA_typef6b47091-5776-40c5-ab79-5b84a499d89bResourceUsage
IntegerVariation order sequence numberSP_ResA_vo_seq1dfae7b9-b7bc-485a-a637-01bfea40fe1bResourceUsage
StringChange order number as specified by userSP_ResA_changeorder_number9258b6ab-e2f8-4c23-a913-eb7eb3832be4ResourceUsage
StringChange order type: V = Variation Order R = Variation Order Request I = Internal Change S = SubcontractedSP_ResA_changeorder_typed932d2fe-6497-48b1-8bfd-e7a5d436f77bResourceUsage



The list of fields for P6

The list of fields that are automatically added to a transfer when source and destination is Safran.

 

DataTypeDescriptionHostSystemIlapTermNameILAPIdPlObjType
BooleanThe option that determines whether the activity's actual and remaining units start date finish date and percent complete are computed automatically using the planned dates planned units and the schedule percent complete. If this option is selected the actual/remaining units and actual dates are automatically updated when project actuals are applied. Use this option to assume that all work for the activity proceeds according to plan.P6_Act_AutoComputeActualsf843ba1d-79c7-4501-8ca6-ff0bbb4b6bfbActivity
StringThe duration type of the activity. One of 'Fixed Units/Time' 'Fixed Duration and Units/Time' 'Fixed Units' or 'Fixed Duration and Units'. For 'Fixed Units/Time' activities the resource units per time are constant when the activity duration or units are changed. This type is used when an activity has fixed resources with fixed productivity output per time period. For 'Fixed Duration and Units/Time' activities the activity duration is constant as the units or resource units per time are changed. This type is used when the activity is to be completed within a fixed time period regardless of the resources assigned. For 'Fixed Units' activities the activity units are constant when the duration or resource units per time are changed. This type is used when the total amount of work is fixed and increasing the resources can decrease the activity duration.P6_Act_DurationType4fc87a47-915f-44d1-85bd-ed772068b6f2Activity
IntegerThe integer representing the critical path this activity is on. The value 1 is the most critical path value 2 is the second most critical path etc.P6_Act_FloatPath9e2d7f3b-7294-41d4-9c6b-44f4f87f8313Activity
IntegerThe integer representing the order in which this object was found on one of the critical paths.P6_Act_FloatPathOrder3175839e-c11c-4f83-9689-13d6cecd077bActivity
BooleanThe flag that indicates whether an activity is on the longest path. Default = 'N'P6_Act_IsLongestPathf3efc069-8841-42f4-93ee-90b4bc0938b7Activity
StringThe activity percent complete type: 'Physical' 'Duration' or 'Units'.P6_Act_PercentCompleteType3580ee70-7894-45d2-8e4d-ad5618d59efeActivity
DateTimeThe date when a suspended task or resource dependent activity should be resumed. The resume date must be later than the suspend date and earlier than the actual finish date. The Suspend/Resume period behaves like a nonworktime on the activity calendar or resource calendar for task and resource dependent activities.P6_Act_ResumeDateb737d819-a3da-4d62-a855-67c0322cf79cActivity
StringThe current status of the activity either 'Not Started' 'In Progress' or 'Completed'.P6_Act_Status76409f37-0d6d-4dc4-b4d3-54945372a3e5Activity
DateTimeThe start date when the progress of a task or resource dependent activity is delayed from. The suspend date must be later than the actual start date which the activity must have. The progress of the activity can be resumed by setting the resume date. The Suspend/Resume period behaves like a nonworktime on the activity calendar or resource calendar for task and resource dependent activities.P6_Act_SuspendDate9352f091-14b9-40bd-a2ce-784dd94a3eb4Activity
StringThe short code assigned to each WBS element for identification. Each WBS element is uniquely identified by concatenating its own code together with its parents' codes.P6_Act_WBSCode323bcbfb-c5ca-45bc-a6a7-c960c526b14dActivity
StringThe name of the WBS element.P6_Act_WBSName04bde157-78c7-4425-92e0-2b01be5d036bActivity
StringThe WBS hierarchy of the activity.P6_Act_WBSPath74add858-ad33-4c3e-9698-cf1acd24f9a2Activity





BooleanThe flag indicating whether new resource/role assignments drive activity dates by default.P6_ResA_DrivingActivityDatesFlaga0e28df2-907d-4300-8c5c-a16ec3efb8ebResourceUsage
FloatThe planned units per time at which the resource is to perform work on this activity. For example a person assigned full time would perform 8 hours of work per day. A department of five people may perform at 5 days per day. This field is named BudgetedUnitsPerTime in Primavera's Engineering & Construction and Maintenance & Turnaround solutions.P6_ResA_PlannedUnitsPerTime2745223b-c107-4f79-965b-bec5d4b60479ResourceUsage
Float(missing)P6_ResA_RemainingUnits9b38fdc9-4103-42ab-9fd4-21efb9048ba8ResourceUsage
FloatThe units per time at which the resource will be performing work on the remaining portion of this activity. For example a person assigned full time would perform 8 hours of work per day. A department of five people may perform at 5 days per day.P6_ResA_RemainingUnitsPerTimeb03f003c-80ce-452a-99af-b0172e1b2cccResourceUsage
StringThe resource type: 'Labor' 'Nonlabor' or 'Material'.P6_ResA_ResourceType210bb608-ac56-4987-915e-c1c11c955625ResourceUsage


Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article